Monday, July 15, 2013

Email


Dear Melissa,,

 

We have completed our review and there are things that look as if all items are included, and some items that do not follow the guidelines that NYSERDA has created. 

 There are 2 issues per building. 1st issue was the occupancy coordination.  Your team has provided the occupancy sensor drawings and that should be fairly cut and dry for NYSERDA.

Potential NYSERDA Incentive for occupancy sensors

Building A = $XXXX

Building B  = $XXXX

Building C= $XXXX

 The second issue is taking incentives based on lighting power density, which is predominantly attributable to the additional decorative lighting allowance in the corridors. The incentives for lighting power savings is currently estimated to be follows:


Building A = $XXXX

Building B  = $XXXX

Building C = $XXXX

 ·         Building A has two independently controls sets of fixtures: Wall sconces, and overhead lighting. When only the overhead lighting is on the design appears to us that it provides a “substantially uniform level of illumination.”  These criteria are the minimum indicated that ASHRAE/NYSERDA require to consider an incentive for the measures.

·         Building B and C have only wall sconces and no overhead lights. Fifty percent of the wall sconces are controlled independently. However, when only half the sconces are on it doesn’t appear to us that there is a “substantially uniform level of illumination”  (i.e., illumination varies between 1.4 to 8.6 fc).  Consequently, it seems less likely that NYSERDA will approve of this measure for these buildings.

Please find attached proposal for additional efforts related to revising the reporting to address changes based on recently received design information.  There is basic coordination and we have broken out the second issue fees based on the building.  Please note that there are no guarantees regarding lighting power incentives which are solely at the discretion of NYSERDA, but we feel you have the best shot with building A.  You can decide how you want to proceed with each building.  Finalizing the packages will take about two weeks when we get the go ahead.

 

Best-

6 comments:

  1. Could you please post the original email that was sent to you? It would help us a lot.

    ReplyDelete
    Replies
    1. Not sure if you are notified, but I had additional correspondence...see below.

      Thanks!

      Delete
  2. This comment has been removed by the author.

    ReplyDelete
  3. There was not an original email. This is based on a series of meetings.

    ReplyDelete
  4. Below is the explanation that, in retrospect, should have been in the original email. comments welcome!


    Draft:

    Melissa,

    The main issue is that we never received coordinated drawings with electrical, lighting and controls; despite requesting it numerous times. These documents are required to support and revisions related to NYSERDA Reporting. The analysis and NYSERDA report were based on general descriptions, that we were given by the consulting team, regarding intentions for the design. NYSERDA requested multiple clarifications and explanations of the energy efficiency measures and we worked very hard to support the design in our responses. Unfortunately, NYSERDA was not willing to accept the EEMs based on the documentation that we had.

    Consequently, under the typical process (for which our contract scope and fee allows) this would have meant removing the measures from the report and losing the associated incentives.

    As a courtesy to the project, we offered you the option of continuing to pursue the measures. Based on NYSERDA’s review, to do so required drawings and other design documentation to support the measures. At our own risk, we’ve coordinated getting this information and looking at it to determine whether we feel that the information seems sufficient to go back to NYSERDA. Based on our review we’ve determined that likelihood of each project receiving the incentive based on actual design information and the nature of NYSERDA’s objections.

    If you decide to continue based your perception of the cost-benefit that we’ve summarized, then it will require additional work to revise report, and continue to discuss the revisions and measures with NYSERDA.

    To date, we’ve expend far greater effort than normal to the project’s benefit trying to capture what we believed were energy efficiency measures that should be recognized despite not being well documented. Alternately, we’ll cease our efforts, and simply revise the report and incentives based on NYSERDA’s comments.

    I’m sorry if you are disappointed with the process, but I hope that you understand that we’ve only tried to do what we believe was in the interest of the projects.

    Let me know if you have additional questions.


    Best regards,
    Emily Kildow
    ________________________________________
    From: Pianko, Melissa [mpianko@Gothamorganization.com]
    Sent: Sunday, July 14, 2013 11:54 AM
    To: Emily Kildow
    Cc: Ian Graham; Lauren Campfield
    Subject: RE: 44th Street Gotham NYSERDA
    I don’t understand why this is an additional scope of work? You guys are being paid a lot for this job already. Please explain why you are asking for more money now – and show me in the existing proposals why it is not already covered. NYSERDA processing is part of what you are supposed to do.

    ReplyDelete
  5. the semi colon after controls should be a comma (controls;) Second line.

    ReplyDelete